Bentec 450 at the planned dress rehearsal
During the first quarter of 2025, the Bentec 450 is undergoing a five-year inspection. The rig had to interrupt its drilling campaign in Hungary, where it has been operating since last year, to carry out this important part of its regular maintenance. The inspection itself is mainly carried out in Lusatia and partly in Bad Bentheim and Hungary. Once completed, the BT450 is expected to be recommissioned and the project will resume during April.
During the five-year inspection of the main parts of the B450 kit, the following was carried out:
- Complete Top Drive inspection, including replacement of critical parts such as main shaft, bearings. This was carried out completely by the manufacturer, Bentec,
Other equipment was inspected by MND DS in Lusatia.
- complete inspection of the flushing pumps, replacement of worn parts, NDT checks
- overhaul of Cathead (hydraulic breakaway), NDT checks, overhaul of hydraulic cylinders
- overhaul of Iron Roughneck ST-120, NDT inspections, repair of hydraulic elements, repair of kinetics
- Complete Crown Block inspection: sandblasting, NDT inspections, bearing replacement, repainting
- complete inspection of Travelling Block (hoist): sandblasting, NDT inspections, bearing replacement, coating
- Complete inspection of Dead Line Anchor: sandblasting, NDT inspection, bearing replacement, coating
- Complete inspection of Rig Floor Winches
- complete inspection of Rotary Table
Inspections included replacement and repair of the internal cooling in the VFD container.
The following measures were carried out on the rig stored in Hungary:
- Replacement of electrical cables on the Mud Tank System.
- inspections of steel structures and lifting points
- adjustment and inspection of injectors on Cummins main generators
- regular checks and inspections on other equipment and accessories of the B450
The shutdown also included fabrication and modification of the Rig floor to Trip tank scavenging drain.
- Production of individual parts was carried out in the Czech Republic
- the modification of the outlet and installation of the new parts was carried out in Hungary
Radovan Jedlička
Head of Sales Department
Other articles
We have upgraded the Bentec 350 - increasing the lifting capacity to 418 tonnes
Our company is pleased to announce a major modification to the Bentec 350, which will increase its lifting capacity from the original 350 to 418 tonnes. This move will allow us to better respond to the growing demand for heavy rigs that has arisen not only in the Oil and Gas sector, but also in the deep geothermal drilling sector.
Places to relax and lots of greenery. The area in Lužice will be transformed into a modern technology park
Not just fix it, but improve it in every way. MND Drilling and Services has a plan to elevate the Lužice site - from a functional, landscape, technological and aesthetic point of view. The tornado caused more than a quarter of a billion crowns worth of damage. Three years on, virtually everything has been repaired. But it doesn't stop there. On the contrary.
Krumvir 3 - four kilometres underground, potentially huge reserves
The deepest borehole in the Czech Republic in the last 30 years has received considerable media attention. Representatives of newspapers, TV and radio stations went to the area around Krumvír in South Moravia, where Bentec 350 is working. MND arranged an excursion for them to show their readers, viewers and listeners what it is like to work on a borehole that goes more than four kilometres underground.