Bentec 450 at the planned dress rehearsal

During the first quarter of 2025, the Bentec 450 is undergoing a five-year inspection. The rig had to interrupt its drilling campaign in Hungary, where it has been operating since last year, to carry out this important part of its regular maintenance. The inspection itself is mainly carried out in Lusatia and partly in Bad Bentheim and Hungary. Once completed, the BT450 is expected to be recommissioned and the project will resume during April.

During the five-year inspection of the main parts of the B450 kit, the following was carried out:

  • Complete Top Drive inspection, including replacement of critical parts such as main shaft, bearings. This was carried out completely by the manufacturer, Bentec,

Other equipment was inspected by MND DS in Lusatia.

  • complete inspection of the flushing pumps, replacement of worn parts, NDT checks
  • overhaul of Cathead (hydraulic breakaway), NDT checks, overhaul of hydraulic cylinders
  • overhaul of Iron Roughneck ST-120, NDT inspections, repair of hydraulic elements, repair of kinetics
  • Complete Crown Block inspection: sandblasting, NDT inspections, bearing replacement, repainting
  • complete inspection of Travelling Block (hoist): sandblasting, NDT inspections, bearing replacement, coating
  • Complete inspection of Dead Line Anchor: sandblasting, NDT inspection, bearing replacement, coating
  • Complete inspection of Rig Floor Winches
  • complete inspection of Rotary Table

Inspections included replacement and repair of the internal cooling in the VFD container.

The following measures were carried out on the rig stored in Hungary:

  • Replacement of electrical cables on the Mud Tank System.
  • inspections of steel structures and lifting points
  • adjustment and inspection of injectors on Cummins main generators
  • regular checks and inspections on other equipment and accessories of the B450

The shutdown also included fabrication and modification of the Rig floor to Trip tank scavenging drain.

  • Production of individual parts was carried out in the Czech Republic
  • the modification of the outlet and installation of the new parts was carried out in Hungary

Radovan Jedlička

Head of Sales Department

Other articles

The Lužice complex following renovation

The second part of Karel Komárek’s two-day visit took him to the refurbished MND Drilling and Services site in Lužice. The project, involving an investment of 250 million crowns, not only saw the restoration of the site, which had been devastated by a tornado, but also its fundamental modernisation — from new operational areas and a central park to a comprehensive rainwater management system.

25.06.2026

Košice as a springboard: MND sets its sights on further geothermal projects

The completion of the boreholes near Košice shows that deep geothermal energy can serve as a stable source of energy even in Central Europe. At the same time, however, it raises questions about where this type of project makes sense and how quickly it can be scaled up. Radovan Jedlička, Head of Business Development at MND Drilling & Services, discusses the potential, limitations and further opportunities.

26.06.2026

How are heavy goods vehicles transported across Europe?

From the perspective of transporting our drilling rigs, 2025 was once again a period of intense activity, meticulous planning and complex logistics. Our fleet of Bentec 250, Bentec 350, Bentec 450 and MD150 rigs was moved between a number of destinations across the whole of Europe during the year. Each such move represents a complex operation requiring an experienced team, detailed coordination and a high level of technical preparedness.
25.06.2026
Privacy and cookie settings 🍪

The website uses cookies to provide services, personalize ads and analyze traffic.

By selecting below you agree to our privacy and cookie policy. You can change your settings at any time.

Customize