Shallow drilling campaign to start next year based on results of latest 3D seismic

For next year, our geologists have prepared a series of wells that they have identified based on the latest large 3D seismic survey. The campaign will start in the second half of the year in the Dubňany and Skoronic area. During December, however, work will begin on the last well of the season - Mikulov 3.

In addition, a pumping trial at the Koryčany well is being completed these days, which will determine whether the project has been successful. By all accounts, the well should be positive, as it is a deposit that is relatively well explored, albeit quite complicated. From a depth of 1 900 metres we should start producing oil.

"This is the severalth well drilled into the deposit, and the saturation and contacts between oil and water or oil and gas are known," says Tomáš Baldrián, head of the geology department.

Work on the Mikulov 3 well, which was originally scheduled to start next year, will begin in December. The target depth is similar to that of Koryčany, at 1,770 metres, and production is to be from 1,650 metres. Probe number 3 is in close proximity to Mikulov 5.

"Five has already reached production and three is targeting the neighbouring cru. The chances there are relatively good, but it's still just exploration. It may turn out that the kra has leaked and we have already produced all the gas with five," Baldrian points out.

The advantage is that Mikulov 3 can start producing immediately because the connection is right next door, so there is no need to build anything. And since the neighbouring probe has completed production, there is not much to wait for. Mikulov 3 should thus contribute to the production plan next year, as it should be productive in a few months.

According to the approved financial plan, the geologists are planning to start the Dambořice 9a well in the first half of the year, which is a deviation from the "Dambořice 9". There will then be a short break and in the second half of the year we will start a campaign of shallow drilling in the Dubňany and Skoronic area. These will be the first wells of the latest 3D seismic survey. "For the first campaign we have selected the Skoronice 1 and 2 projects. They target both oil and gas and are the easiest to access. If they are positive, other projects will follow," predicts Tomas Baldrian.

In addition, Hodonín geologists are now working intensively on data interpretation at the Zukivska licence in Ukraine, where 3D seismic measurements were carried out earlier this year. They intend to mark the targets later this year and plan to drill the first exploration well next year.

"This is high quality data showing structures associated with the salt plume. We expect to prepare two to three projects with significant potential," concludes geologist Tomas Baldrián.

Martin Beneš
Editor-in-Chief

Other articles

Disposal of Ždánice probes: closing another chapter of mining

At the start of 2023, the decommissioning of three wells in the Ždánice area was successfully completed. This symbolically marked the end of a chapter in the long history of oil and gas extraction in this region. Each well had a different history and significance, but what they had in common was that they had fulfilled their purpose and, upon reaching the end of their life cycle, were professionally and safely secured in a permanent state.

16.03.2026

When the team creates contrasts, the company grows, says Jana Hamršmídová

The energy sector is often described as a male-dominated world. However, Jana Hamršmídová, Director of the Energy Division at MND, says that the key lies not in fighting for quotas, but in active collaboration, mutual respect and diversity within teams. In this interview, she talks about changing corporate culture, fostering respect and balancing career and family life.
16.03.2026

Oil production at the Lanžhot field ends after 70 years

The site is awaiting reclamation and restoration to nature. After almost seven decades, mining at the Lanžhot deposit, the southernmost oil deposit in the Czech Republic, is coming to an end. In a remote forest area at the confluence of the Dyje and Kyjovka rivers, in a location that is located in a protected zone and whose administration is becoming increasingly demanding from a legislative point of view, only a few wells remain today. These will be gradually closed in the coming years and the entire area will be prepared for reclamation.

13.12.2025
Privacy and cookie settings 🍪

The website uses cookies to provide services, personalize ads and analyze traffic.

By selecting below you agree to our privacy and cookie policy. You can change your settings at any time.

Customize