Second well test of Dambořice 9

The last drilling here was in the summer of 2023. While the frogs were croaking then, now, at the end of winter, there are plenty of hares and deer roaming the surrounding fields. And in the evenings, beavers are regularly seen cupitating in the adjacent Burnt Creek.

The original "nine" targeted the horizon at a depth of 3,100 metres and drilled essentially perpendicularly downwards. Dambořice 9A is targeting a similar depth, however, a deviation is made at 900 metres. This means that the original borehole is being sidetracked.
"The deviation is to a position that is 50 metres structurally higher, 800 metres from the original target. It's at an angle of about 30 degrees," explains Tomas Baldrián, director of the geology department at MND.
And why is it being drilled again in the same place? Simply because the original project did not turn out positively, but provided very promising information.
"The Dambořice 9 well intercepted a 250 metre complex of palaeogene sands. We tested the surface of the complex and achieved an inflow of reservoir water with a percentage of oil - up to 12 percent. This indicates that we could be somewhere close to the oil-water contact of the oil reservoir, which is in a higher structural position," added Tomas Baldrian.
The Dambořice 9 prospect is analogous to the Borkovany deposit in the deeper part of the palaeogene fill of the Nesvačil trench. Prospective resources (expected reserve size) here are 330 million cubic meters of gas.
Martin Beneš
Editor-in-Chief

Other articles

November teambuilding MND ES and MND GS

On Thursday, 13 November, a planned team-building day was held for employees of MND Energy Storage and MND Gas Storage, offering a combination of good food, sporting activities and a relaxing evening programme. The event was divided into three parts – a joint lunch, a badminton tournament and a guided wine tasting.

13.12.2025

Oil on the rails

Four times more crude oil than before is sent by MND from the Lusatian railway station to Kralupy nad Vltavou these weeks. The reason for this is the termination of transport via the Druzhba pipeline. All the crude oil produced must be transported by tanker - first by truck, then by rail.

19.09.2025

Disposal of probes in Prušánky

In March 2025, the abandonment of three production wells in the Prušánky area was successfully completed - specifically wells Prušánky 4b, 6 and 8. Together, these probes opened and produced the Labe horizon in the Middle Baden on the subsiding crust of the Schrattenberg fault system.

19.09.2025
Privacy and cookie settings 🍪

The website uses cookies to provide services, personalize ads and analyze traffic.

By selecting below you agree to our privacy and cookie policy. You can change your settings at any time.

Customize