Disposal of probes in Prušánky

In March 2025, the abandonment of three production wells in the Prušánky area was successfully completed - specifically wells Prušánky 4b, 6 and 8. Together, these probes opened and produced the Labe horizon in the Middle Baden on the subsiding crust of the Schrattenberg fault system.

The liquidation took place on the following dates:

  • Prušánky 6: 6-13 March 2025
  • Prušánky 4b: 14-18 March 2025
  • Prušánky 8: 19-25 March 2025

Mining history

  • Prušánky 4b was an exploration well that discovered a natural gas field in July 2006. The well produced both gas (51.13 million m³ in total) and oil (4,795.58 m³), with an average daily oil production of 28 m³ in 2013.
  • Prusanky 8, a well drilled in 2009, verified the northern extension of the field. Production continued until April 2019, when the horizon was watered. A total of 62.68 m³ of gas and 11,407 m³ of gasoline were produced.
  • The Pruzhany 6 well, drilled in 2013, was designed to help complete the oil zone but only captured the gas portion of the field. Between 2014 and 2019, 13.86 million m³ of gas and 41 m³ of gasoline were produced.

After evaluating the electrofracture measurements, no further saturation was detected in the overburden horizons, and therefore it was decided to dispose of the probes after production was completed. This brings to an end almost 20 years of production in the Prušánek area, which has yielded significant energy resources in the form of natural gas, oil and gasoline.

Petr Ořeský

Head of Drilling, POS and Supervision

Other articles

The life cycle of a borehole ends with reclamation. What does it involve?

The drilling and subsequent disposal of the probe is a fascinating process that can be likened to the life cycle from birth to death. Every well, whether exploratory or production, has its own life story. Repot is now bringing you a series that will present interesting reclamations of our specific sites one by one. But in this issue, let's talk in general terms about what such reclamation looks like, why it's done in the first place, and how much it actually costs.

01.03.2025

The first well at Zukivska will be the most important thing this year. The reserves there are huge.

Successful development of the Tynivska licence, the Girska extension, the acquisition of Pivdeno Girska and the plan for the first well at Zhukyvska. MND has moved up a gear in Ukraine. And they are on track for further milestones. This year, the company wants to reach 150 million cubic meters of gas production in the country. Lukáš Svozil is in charge of MND's Ukrainian operations and spends much of his time on the road.

"Our success is built on two fundamental pillars that complement each other. The first pillar is a strong team in Lviv. The second is the great support from Hodonin," he says.

01.03.2025

He believed in Tynivskaya's success, now Volodya Radelytskyi has the same feeling about Zhukyvskaya

Geology is often about experience and intuition in interpreting data. 3D seismic measurements may produce hard data, but they can reveal a lot, and the human factor still plays a significant role. Volodya Radelytskyi knows the underground structures of western Ukraine very well. It was he who strongly recommended that MND buy the Tynivskaya licence. The swampy area at first sight did not have such potential.

01.03.2025
Privacy and cookie settings 🍪

The website uses cookies to provide services, personalize ads and analyze traffic.

By selecting below you agree to our privacy and cookie policy. You can change your settings at any time.

Customize